Use the information in the table to sketch the network and compute early and late start times.
 Activity  Time  Predecessor  A 8 B 4 A  C 5 B, F  D 12 A E8 D  F 4 D G9 E, F \begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 8 & \\\hline \text { B } & 4 & \text { A } \\\hline \text { C } & 5 & \text { B, F } \\\hline \text { D } & 12 & \text { A } \\\hline E & 8 & \text { D } \\\hline \text { F } & 4 & \text { D } \\\hline G & 9 & \text { E, F } \\\hline\end{array}


Definitions:

Free Trade

A policy or practice of trading between countries, with minimal restrictions or tariffs, to encourage economic exchange.

Economic Well-being

Refers to the overall quality of life based on financial stability, access to resources, and the ability to meet basic needs.

Transnational Corporations

are business entities that operate in multiple countries but are headquartered in one country, significantly influencing global economics and politics.

Globalization

The process of interaction and integration among people, companies, and governments worldwide, often driven by trade and investment and aided by information technology.

Related Questions