An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of $100,000.Due to slippage on the critical path you need to reduce this activity by three weeks.If the subcontractor informs you that the activity can be completed in 16 weeks for $200,000,what is the slope for the activity?
Direct Labor Hour
Direct labor hour refers to the time spent by workers directly involved in the production of goods or services.
Overhead Applied
A portion of overhead costs assigned to a particular cost object based on a predetermined rate.
Direct Labor Efficiency Variance
The difference between the budgeted amount of direct labor required to produce an output and the actual direct labor used.
Favorable
A term used in budgeting and finance to indicate results that are better than expected, such as lower costs or higher revenues.
Q10: Risks can be quantified by multiplying the
Q24: A project has the activity duration
Q32: Mathematical programming is sometimes used to generate
Q37: Project risk is lowest during the:<br>A) Concept
Q39: XYZ project organization has one workstation that
Q40: The coefficient of variation is a measure
Q56: Two measures of the risk premium are
Q59: A project that consists of six
Q84: Sketch a network and use it as
Q97: Explain the difference between normal and expedited