A Project Consists of Four Consecutive Tasks That Have Average

question 45

Multiple Choice

A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table.Use Newbold's model to determine the aggregated one sigma buffer for this project.  Activity  Average  Worst-Case A1020B1525 C 2030D2535\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Average } & \text { Worst-Case } \\\hline A & 10 & 20 \\\hline B & 15 & 25 \\\hline \text { C } & 20 & 30 \\\hline D & 25 & 35 \\\hline\end{array}


Definitions:

Right to Vote

The entitlement of citizens to participate in their government's election process to choose leaders and voice opinions on legislation and policies.

Thirteenth Amendment

An amendment to the U.S. Constitution that abolished slavery and involuntary servitude, except as a punishment for a crime.

Slavery

A system in which individuals are owned by others, deprived of personal freedom and forced to perform labor or services without compensation.

Plessy v. Ferguson

The 1896 Supreme Court decision that upheld racial segregation under the "separate but equal" doctrine, later overturned by Brown v. Board of Education in 1954.

Related Questions