Examlex

Solved

A Project Consists of Six Consecutive Tasks That Have Average

question 17

Multiple Choice

A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in weeks) as shown in the table.Use Newbold's method to determine the aggregated two sigma buffer for this project.  Activity  Average  Worst-Case A1014B24C612D813.5E912F57.5\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Average } & \text { Worst-Case } \\\hline \mathrm { A } & 10 & 14 \\\hline \mathrm { B } & 2 & 4 \\\hline \mathrm { C } & 6 & 12 \\\hline \mathrm { D } & 8 & 13.5 \\\hline \mathrm { E } & 9 & 12 \\\hline \mathrm { F } & 5 & 7.5 \\\hline\end{array}


Definitions:

Visible Recognition

The acknowledgment or appreciation of an individual's or group's efforts or achievements in a public and noticeable manner.

Influential Morality

A concept that deals with the impact moral values have on guiding behavior and influencing others.

Transactional Leadership

A leadership style focused on the exchanges between leaders and followers, emphasizing rewards and punishments to motivate performance.

Contingent Reward

A leadership approach that involves the exchange of rewards for achieving defined performance standards.

Related Questions