Examlex

Solved

Use the Project Information in the Table to Resolve Resource

question 64

Multiple Choice

Use the project information in the table to resolve resource conflicts,identify the critical chain and critical path,and create feeder buffers.A feeder buffer should be placed immediately before:  Activity  Predecessor  Length  Resource  Activity  Predecessor  Length  Resource A11PDC13PBA7ME12XCB8 W FE14M\begin{array} { | l | l | l | l | l | l | l | l | } \hline \text { Activity } & \text { Predecessor } & \text { Length } & \text { Resource } & \text { Activity } & \text { Predecessor } & \text { Length } \text { Resource } \\\hline \mathrm { A } & - & 11 & \mathrm { P } & \mathrm { D } & \mathrm { C } & 13 & \mathrm { P } \\\hline \mathrm { B } & \mathrm { A } & 7 & \mathrm { M } & \mathrm { E } & - & 12 & \mathrm { X } \\\hline \mathrm { C } & \mathrm { B } & 8 & \mathrm {~W} & \mathrm {~F} & \mathrm { E } & 14 & \mathrm { M } \\\hline\end{array}


Definitions:

Related Questions