Examlex

Solved

Use the Project Described in the Table to Determine the Total

question 33

Multiple Choice

Use the project described in the table to determine the total resources required for this project during week 1 if a worker is expected to devote half-time (four hours per day) to this project.Assume that the project work is conducted on a 5-day-per-week basis.  Activity  Duration  Predecessor A5 days B4 days AC5 days  A D6 days BE6 days C,DF6 days E\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Duration } & \text { Predecessor } \\\hline \mathrm { A } & 5 \text { days } & - \\\hline \mathrm { B } & 4 \text { days } & \mathrm { A } \\\hline \mathrm { C } & 5 \text { days } & \text { A } \\\hline \mathrm { D } & 6 \text { days } & \mathrm { B } \\\hline \mathrm { E } & 6 \text { days } & \mathrm { C } , \mathrm { D } \\\hline \mathrm { F } & 6 \text { days } & \mathrm { E } \\\hline\end{array}


Definitions:

Crystal Ball

In forecasting and predictive analysis, a tool or method that allows for the estimation of future conditions or occurrences.

Tornado Charts

A graphical method used in sensitivity analysis to show the effect of varying different parameters on a particular outcome.

Monte Carlo Simulation

A computational algorithm that relies on repeated random sampling to obtain numerical results, often used in physical and mathematical problem-solving.

Correlation Coefficients

Statistical measures that quantify the strength and direction of the linear relationship between two variables, ranging from -1 (perfect negative correlation) to 1 (perfect positive correlation).

Related Questions