Examlex

Solved

Use the Project Described in the Table to Determine the Total

question 47

Multiple Choice

Use the project described in the table to determine the total resources required for this project on day 10 if a worker is expected to devote half-time (four hours per day) to this project.Assume that the project work is conducted on a 5-day-per-week basis.  Activity  Duration  Predecessor A5 days B4 days AC5 days  A D6 days BE6 days C,DF6 days E\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Duration } & \text { Predecessor } \\\hline \mathrm { A } & 5 \text { days } & - \\\hline \mathrm { B } & 4 \text { days } & \mathrm { A } \\\hline \mathrm { C } & 5 \text { days } & \text { A } \\\hline \mathrm { D } & 6 \text { days } & \mathrm { B } \\\hline \mathrm { E } & 6 \text { days } & \mathrm { C } , \mathrm { D } \\\hline \mathrm { F } & 6 \text { days } & \mathrm { E } \\\hline\end{array}


Definitions:

Full Release

A legal agreement in which one party permanently relinquishes all claims against another.

Novation

The process of replacing one obligation with another by mutual agreement.

Entire Agreement

A clause in a contract that declares the contract to be the complete and final agreement between the parties, superseding all prior negotiations, promises, or representations.

Privity of Contract

The principle that a contract directly affects and grants enforceable rights only to the parties involved in the contract agreement.

Related Questions