Use the Earned Value Table for Project Makeready to Calculate

question 13

Multiple Choice

Use the earned value table for Project Makeready to calculate their schedule performance index. Use the earned value table for Project Makeready to calculate their schedule performance index.   A)  1.46 B)  0.68 C)  0.79 D)  1.26