Use the Earned Value Table (All Amounts Indicated Are Dollars)to

question 86

Multiple Choice

Use the earned value table (all amounts indicated are dollars) to determine the earned value to the nearest hundred dollars given the indicated state of the project. Use the earned value table (all amounts indicated are dollars) to determine the earned value to the nearest hundred dollars given the indicated state of the project.   A)  $16,900 B)  $14,900 C)  $14,400 D)  $13,200