Bronze Brick Company uses the following rule to determine whether materials usage variances should be investigated:
A materials usage variance will be investigated when the variance is greater than either $5,000 or 12% of the standard cost.
During May, the company purchased and used 11,000 kg of concrete for $5 per kilogram. It was able to make 20,000 bricks. Its standard quantity of materials allowed is 0.50 kg of concrete per brick at a standard price of $6.50 per kilogram.
Required:
A. Determine Bronze's material usage variance and whether it is favourable or unfavourable.
B. Should the variance be investigated?
Yield To Maturity
The total return anticipated on a bond if the bond is held until its maturity date, expressed as an annual rate.
Duration
A measure of the sensitivity of a bond's or fixed income portfolio's price to changes in interest rates, often used to manage interest rate risk.
Modified Duration
A measure of the sensitivity of a bond's price to changes in interest rates, specifically reflecting how much the duration changes for a 1% change in yield.
Macaulay Duration
A measure of the weighted average time until a bond or fixed income portfolio's cash flows are received, used to gauge interest rate sensitivity.
Q4: 44.7 <span class="ql-formula" data-value="\times"><span class="katex"><span
Q6: 1/3 <span class="ql-formula" data-value="\times"><span class="katex"><span
Q6: 18 mg = _ mcg
Q7: 125 : 20 :: 300 : x
Q9: When budgeting at the activity level, with
Q87: In the negotiated transfer pricing, the buying
Q98: Difference between the actual amount and the
Q115: Refer to Cold Cream Company. Assume
Q120: Which term best categorizes the kaizen costing
Q148: Kaizen means continuous improvement.