A Company Produces Two End-Items: Products a and B \quad

question 39

Essay

A company produces two end-items: products A and B. They are concerned about the loading on their Finish Shop and are trying to develop a rough?cut capacity plan. To finish product A two hours are required and for product B one hour. Total hours available in the Finish Shop are 100. They have the following weekly production information:
\quad \quad \quad \quad \quad \quad \quad \quad \quad  Week \text { Week } End Item 123456A400400400B030003030\begin{array}{|c|r|r|r|r|r|r|}\hline \text { End Item } & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \mathrm{A} & 40 & 0 & 40 & 0 & 40 & 0 \\\hline \mathrm{B} & 0 & 30 & 0 & 0 & 30 & 30 \\\hline\end{array}
a. What is the total hourly load on the Finish Shop in week 3?
b. In what week is the Finish Shop overloaded?


Definitions:

Clear-Cut

A forestry practice where all the trees in an area are uniformly cut down, often leading to ecological disruptions and loss of habitat.

Water Well Drilling

The process of creating a hole in the earth's surface for the purpose of accessing underground water sources.

Toxic Chemicals

Substances that can cause harm to organisms through chemical reactions or environmental exposure.

Related Questions