A company is faced with seven tasks that have to be processed through two work centers, work center I and then center II. Assume work center I works continuously and that they are using Johnson's rule. Work centers need not change over to new jobs at the same time. Data appears below in hours:
 ask  Wark Center I  Work Center II  A 2.583.47B1.665.84C2.712.41D5.521.99E3.387.62F5.221.73 G 2.891.11\begin{array} { | c | c | c | } \hline \text { ask } & \text { Wark Center I } & \text { Work Center II } \\\hline \text { A } & 2.58 & 3.47 \\\hline \mathrm { B } & 1.66 & 5.84 \\\hline C & 2.71 & 2.41 \\\hline \mathrm { D } & 5.52 & 1.99 \\\hline E & 3.38 & 7.62 \\\hline \mathrm { F } & 5.22 & 1.73 \\\hline \text { G } & 2.89 & 1.11 \\\hline\end{array}
a. What is the sequence of tasks?
b. What is the time in hours to complete all the tasks in both work centers?
c. What is the total idle time in hours for work center I?
d. What is the total idle time in hours for work center II?


Definitions:

Client Specifications

Client specifications are detailed descriptions provided by a client outlining the requirements, standards, and criteria for a project or product.

Quality

Good or service that is free of deficiencies.

Prices

The amounts of money expected, required, or given in payment for something.

Dependability of Delivery

The reliability with which a company or supply chain delivers products or services to its customers in the promised time frame.

Related Questions