Consider the Project Network and Data Shown Below ADetermine the Critical Path and the Project Completion Time

question 43

Essay

Consider the project network and data shown below:  Consider the project network and data shown below:    \begin{array}{|c|c|r|r|r|r|} \hline&& \text { Normal }& \text { Crash }  & \text { Normal } & \text { Crash }  & \text { Crash Cost }\\ \text { Activity } & \text { Slack } & \text { Time } & \text { Time } & \text { Cost } & \text { Cost } & \text { Per Week }\\ \hline \mathrm{A} & 0 & 7 & 4 & \$ 400 & \$ 750 \\ \hline \mathrm{B} & 1 & 12 & 9 & \$ 1,000 & \$ 2,200 \\ \hline \mathrm{C} & 0 & 7 & 6 & \$ 800 & \$ 1,100 \\ \hline \mathrm{D} & 0 & 6 & 5 & \$ 600 & \$ 1,000 \\ \hline \mathrm{E} & 0 & 8 & 6 & \$ 1,200 & \$ 2,200 \\ \hline \mathrm{F} & 9 & 3 & 2 & \$ 800 & \$ 1,000 \\ \hline \mathrm{G} & 9 & 3 & 2 & \$ 500 & \$ 650 \\ \hline \mathrm{H} & 0 & 4 & 3 & \$ 400 & \$ 600 \\ \hline \mathrm{I} & 0 & 6 & 5 & \$ 900 & \$ 1,300 \\ \hline \end{array}    a.Determine the critical path and the project completion time. b.Determine the crash cost per week for all activities c.Which activities need to be crashed to reduce the project's completion time by 4 weeks? How much does this cost?  Normal  Crash  Normal  Crash  Crash Cost  Activity  Slack  Time  Time  Cost  Cost  Per Week A074$400$750B1129$1,000$2,200C076$800$1,100D065$600$1,000E086$1,200$2,200F932$800$1,000G932$500$650H043$400$600I065$900$1,300\begin{array}{|c|c|r|r|r|r|}\hline&& \text { Normal }& \text { Crash } & \text { Normal } & \text { Crash } & \text { Crash Cost }\\\text { Activity } & \text { Slack } &\text { Time } & \text { Time } & \text { Cost } & \text { Cost } & \text { Per Week }\\\hline \mathrm{A} & 0 & 7 & 4 & \$ 400 & \$ 750 \\\hline \mathrm{B} & 1 & 12 & 9 & \$ 1,000 & \$ 2,200 \\\hline \mathrm{C} & 0 & 7 & 6 & \$ 800 & \$ 1,100 \\\hline \mathrm{D} & 0 & 6 & 5 & \$ 600 & \$ 1,000 \\\hline \mathrm{E} & 0 & 8 & 6 & \$ 1,200 & \$ 2,200 \\\hline \mathrm{F} & 9 & 3 & 2 & \$ 800 & \$ 1,000 \\\hline \mathrm{G} & 9 & 3 & 2 & \$ 500 & \$ 650 \\\hline \mathrm{H} & 0 & 4 & 3 & \$ 400 & \$ 600 \\\hline \mathrm{I} & 0 & 6 & 5 & \$ 900 & \$ 1,300 \\\hline\end{array}

a.Determine the critical path and the project completion time.
b.Determine the crash cost per week for all activities
c.Which activities need to be crashed to reduce the project's completion time by 4 weeks? How much does this cost?


Definitions:

Fertilized Oocyte

A female egg cell that has combined with a sperm cell, initiating the development of a new organism.

Granulosa

Cells surrounding the oocyte in the ovary, playing a key role in the development and hormone production of the ovarian follicles.

Cumulus Mass

A cluster of cells that surround an oocyte, or egg cell, providing it with nutrients and support during development.

Theca Interna

Inner vascular layer of the theca of the secondary and mature follicle; produces estrogen and contributes to the formation of the corpus luteum after ovulation.

Related Questions