Job a Has a Flow Time of 20 Days, Job

question 72

Short Answer

Job A has a flow time of 20 days, job B has a flow time of 13 days, job C has a flow time of 12 days, and job D has a flow time of 15 days. If the time it takes to finish all four jobs (as a whole batch) is 15 days, what is the average number of jobs in the system?