In Making a Backward Pass Through a Network, Activity L

question 89

Multiple Choice

In making a backward pass through a network, activity L has an activity time of 4 and immediately precedes activities M, P, and T. The late start times for activities M, P, and T are 22, 17, and 27, respectively. The late finish times for activities M, P, and T are 29, 27, and 33, respectively. What is the late finish time for activity L?


Definitions:

FCC

The Federal Communications Commission, an independent U.S. government agency responsible for regulating interstate and international communications by radio, television, wire, satellite, and cable.

Public Affairs

Matters that involve the government and its policies, and how these interact with the public or influence society.

Professional Standard

Guidelines and criteria established by professions to ensure quality, competence, and ethical practice among its members.

Nonpartisanship

An approach to governance or policies that does not formally align with partisan political parties or biases.

Related Questions