Examlex

Solved

An Activity in a Network Diagram Has an Optimistic Time

question 13

Multiple Choice

An activity in a network diagram has an optimistic time estimate of seven days, a most likely time estimate of 11 days, and a pessimistic time estimate of 19 days. Its variance is _________.


Definitions:

Related Questions