The standard factory overhead rate is $12 per machine hour ($10 for variable factory overhead and $2 for fixed factory overhead)based on 100% capacity of 42,000 machine hours.The standard cost and the actual cost of factory overhead for the production of 2,000 units were as follows:
The standard factory overhead rate is $12 per machine hour ($10 for variable factory overhead and $2 for fixed factory overhead)based on 100% capacity of 42,000 machine hours.The standard cost and the actual cost of factory overhead for the production of 2,000 units were as follows:     Determine the (a)volume variance, (b)controllable variance,and (c)total factory overhead cost variance.
Determine the (a)volume variance, (b)controllable variance,and (c)total factory overhead cost variance.