A Project Consists of the Following Activities

question 35

Multiple Choice

A project consists of the following activities:
A project consists of the following activities:    Table 9.1 -Using Table 9.1,the earliest finish (EF) time for activity D is A) 7 weeks. B) 13 weeks. C) 20 weeks. D) 30 weeks.
Table 9.1
-Using Table 9.1,the earliest finish (EF) time for activity D is