A Project Consists of the Following Activities

question 18

Multiple Choice

A project consists of the following activities:
A project consists of the following activities:    Table 9.1 -Using Table 9.1,the latest start (LS) time for activity B is A) 5 weeks. B) 8 weeks. C) 13 weeks. D) 14 weeks.
Table 9.1
-Using Table 9.1,the latest start (LS) time for activity B is