The Following Table of Probabilistic Time Estimates (In Weeks)and Activity

question 42

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the probability that the project could be completed in 34 weeks or less is approximately A) 0.86. B) 0.89. C) 0.91. D) 0.96.
Table 9.2
-Using Table 9.2,the probability that the project could be completed in 34 weeks or less is approximately


Definitions:

Fragment

A sentence fragment is an incomplete sentence that lacks a subject, a verb, or does not express a complete thought.

Fiercely Competitive

engaging in activities or endeavors with intense determination to succeed or win, often beyond the norm.

High Level

A term describing something that is of a superior or advanced status, complexity, or degree in a particular context.

Late 1600s

A historical period referring to the final decades of the 17th century, a time marked by significant cultural, political, and technological changes.

Related Questions