Examlex

Solved

The Estimated Mean Time for an Activity with a Most

question 93

Multiple Choice

The estimated mean time for an activity with a most likely time (m) equal to 12 weeks,an optimistic time (a) equal to 9 weeks,and a pessimistic time (b) equal to 18 weeks is