The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the probability that the project could be completed in 34 weeks or less is approximately A) 0.86. B) 0.89. C) 0.91. D) 0.96.
Table 9.2
-Using Table 9.2,the probability that the project could be completed in 34 weeks or less is approximately


Definitions:

Person-Centered Approach

A counseling and therapeutic framework focusing on client autonomy and the therapist's empathy and unconditional positive regard.

Projective Tests

Psychological assessment tools that use ambiguous stimuli to elicit responses revealing hidden emotions and internal conflicts.

Five-Factor Theory

A model that outlines the five broad dimensions of personality as openness, conscientiousness, extraversion, agreeableness, and neuroticism.

Humanistic Approach

A psychological perspective emphasizing individual potential for growth and the role of unique perceptions in guiding behavior and mental processes.

Related Questions