The Following Table of Probabilistic Time Estimates (In Weeks)and Activity

question 74

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the probability that the project will take longer than 33 weeks to complete is approximately A) 0.19. B) 0.32. C) 0.68. D) 0.81.
Table 9.2
-Using Table 9.2,the probability that the project will take longer than 33 weeks to complete is approximately


Definitions:

Rebounds

In sports, the act of successfully retrieving the ball after a missed shot.

Geometric Sequence

A numerical series where each number after the first is determined by multiplying the prior number by an unchanging, non-zero numerical value, denoted as the common ratio.

Partial Sum

A partial sum is the sum of the first n terms of a sequence, often used in the context of series to understand the progression or to investigate convergence.

N Th

In mathematics, "n-th" refers to an unspecified member of a sequence, indicating its position with the variable n.

Related Questions