A project consists of the following four activities with activity times in days:
A project consists of the following four activities with activity times in days:     Table 9.3 -Using Table 9.3,the earliest start (ES) time for activity B is A) 5 days. B) 6 days. C) 11 days. D) 14 days.
Table 9.3
-Using Table 9.3,the earliest start (ES) time for activity B is