If the Following Jobs Are Sequenced According to the SPT

question 32

Multiple Choice

If the following jobs are sequenced according to the SPT rule then job B is completed on day (assume zero for today's date)
If the following jobs are sequenced according to the SPT rule then job B is completed on day (assume zero for today's date)    A) 6. B) 14. C) 15. D) 22