question 29

Multiple Choice

If the following jobs are sequenced according to the LPT rule then the maximum job tardiness (in days) is (assume zero for today's date)
If the following jobs are sequenced according to the LPT rule then the maximum job tardiness (in days) is (assume zero for today's date)    A) 7 days. B) 10 days. C) 20 days. D) 25 days.