Examlex

Solved

If the Following Jobs Are Sequenced According to the SLACK

question 34

Multiple Choice

If the following jobs are sequenced according to the SLACK rule then the mean tardiness (in days) for all jobs is (assume zero for today's date)
If the following jobs are sequenced according to the SLACK rule then the mean tardiness (in days) for all jobs is (assume zero for today's date)    A) 11.25 days. B) 9 days. C) 20 days. D) 12.5 days.