Uhura Enterprises provides consulting services for customers. Consultants are brought in for two-hour shifts. A consultant will spend one full hour with a customer. The customers remain for that hour and then leave. Each consultant is paid $25 per hour. Let Xi represent the number of consultants starting their shift at hour i, (i = 1,2,3,4) . The firm wishes to minimize salary costs while satisfying demand. Customer demand is as follows.
1:00-2:00 4
2:00-3:00 5
3:00-4:00 10
4:00-5:00 4
5:00-6:00 8
What is the proper objective function?