Consider a project having the following seven activities:
Optimistic Most likely Pessimistic
Immediate Time (o)Time (m)Time (p)
Activity Predecessors (weeks)(weeks)(weeks)
A none 4 7 9
B none 3 5 8
C A 2 4 6
D A, B 6 9 9
E C, D 5 5 5
F B 2 5 9
G E, F 3 3 6
(a)What is the expected time for each activity?
(b)What is the expected project completion time?
(c)What is the critical path?
(d)What is the variance for each activity?
(e)What are the expected time and variance of each path?
(f)What is the probability that the project will be completed in less than 22 weeks?
Simplify
To make something easier to understand or to reduce to a simpler form.
Canadian Dollar
The official currency of Canada, represented by the symbol "$" or the code "CAD".
U.S. Dollar
The official currency of the United States, widely used for international transactions and as a reserve currency.
Collect Like Terms
Combining algebraic terms with the same variable factors into a single term by adding or subtracting their coefficients.
Q8: No matter how bad the boss:<br>A) Report
Q9: _ is when a receiver interprets the
Q21: MRP develops a time-phased schedule that shows
Q52: What is a transfer batch?<br>A)the quantity of
Q59: Information in the inventory records file that
Q62: Make an effort to control your _
Q78: Demand-based options include two reactive options and
Q98: In critical path scheduling, slack is computed
Q102: A _ is one or more people
Q120: The following jobs are waiting to be