Consider a project having the following ten activities:
Normal Normal Crash Crash Maximum
Immediate Time Cost Time Cost Weeks
Activity Predecessors (weeks) ($) (weeks) ($) Reduced
A none 7 3,000 6 6,000 1
B A 8 5,000 6 9,000 2
C A 2 2,000 1 3,000 1
D A 4 3,000 4 3,000 0
E B, C 9 4,000 7 6,000 2
F C, D 6 4,000 4 9,000 2
G E 2 3,000 2 3,000 0
H E, F 9 4,000 7 7,000 2
I G 1 4,000 1 4,000 0
J H, I 8 2,000 6 7,000 2
(a)What is the expected project completion time?
(b)What is the critical path?
(c)What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks? by five weeks?
Syllabus
An academic document that outlines the structure, content, and evaluation methods of a course.
Instructor's Expectations
Instructor's expectations are the standards and requirements that an educator has for their students' performance and behavior in a course.
Adjuncts
Part-time faculty members hired by educational institutions often to teach specific courses.
Office Hours
Designated times set by educators when they are available to meet with students to discuss course materials, assignments, or other concerns.
Q5: Calculate the total cost to meet the
Q9: A leader who makes decisions based on
Q11: When reviewing missed phone messages:<br>A) Not return
Q13: _ is a key element of effective
Q51: Develop a chase aggregate plan without inventory
Q53: Slim-Quick Inc. produces a variety of nutritional
Q58: Which of the following is most likely
Q64: Evaluating an aggregate plan in terms of
Q69: Medical benefits include:<br>A) Physician and hospital visits<br>B)
Q93: Effective communication is necessary for workplace success.