Consider a project having the following ten activities:
Normal Normal Crash Crash Maximum
Immediate Time Cost Time Cost Weeks
Activity Predecessors (weeks) ($) (weeks) ($) Reduced
A none 7 3,000 6 6,000 1
B A 8 5,000 6 9,000 2
C A 2 2,000 1 3,000 1
D A 4 3,000 4 3,000 0
E B, C 9 4,000 7 6,000 2
F C, D 6 4,000 4 9,000 2
G E 2 3,000 2 3,000 0
H E, F 9 4,000 7 7,000 2
I G 1 4,000 1 4,000 0
J H, I 8 2,000 6 7,000 2
(a)What is the expected project completion time?
(b)What is the critical path?
(c)What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks? by five weeks?


Definitions:

Syllabus

An academic document that outlines the structure, content, and evaluation methods of a course.

Instructor's Expectations

Instructor's expectations are the standards and requirements that an educator has for their students' performance and behavior in a course.

Adjuncts

Part-time faculty members hired by educational institutions often to teach specific courses.

Office Hours

Designated times set by educators when they are available to meet with students to discuss course materials, assignments, or other concerns.

Related Questions