In Making a Backward Pass Through a Network, Activity L

question 89

Multiple Choice

In making a backward pass through a network, activity L has an activity time of 4 and immediately precedes activities M, P, and T. The late start times for activities M, P, and T are 22, 17, and 27, respectively. The late finish times for activities M, P, and T are 29, 27, and 33, respectively. What is the late finish time for activity L?


Definitions:

Dutch Auction

A bidding strategy where the auctioneer starts with a high asking price which is lowered until some participant is willing to accept the auctioneer's price.

Selling Shares

The act of disposing of ownership in a company by selling stock in exchange for cash or other compensation.

Subscription Price

The cost that investors pay to acquire securities during an offering before they are available on the open market.

Rights-On Period

A specific time frame during which shareholders have the right to buy additional shares at a predetermined price before the offer is open to others.

Related Questions