Consider a project having the following ten activities:
Immediate
Activity Predecessors Time (weeks)
A none 7
B none 3
C A 5
D A, B 6
E C, D 4
F D 4
G C 9
H E, G 8
I E, F 6
J H, I 5
(a)What is the critical time?
(b)What is the critical path?
(c)What is the slack for each activity?