Examlex

Solved

Consider a Project Having the Following Seven Activities

question 73

Essay

Consider a project having the following seven activities:
Optimistic Most likely Pessimistic
Immediate Time (o)Time (m)Time (p)
Activity Predecessors (weeks)(weeks)(weeks)
A none 4 7 9
B none 3 5 8
C A 2 4 6
D A, B 6 9 9
E C, D 5 5 5
F B 2 5 9
G E, F 3 3 6
(a)What is the expected time for each activity?
(b)What is the expected project completion time?
(c)What is the critical path?
(d)What is the variance for each activity?
(e)What are the expected time and variance of each path?
(f)What is the probability that the project will be completed in less than 22 weeks?


Definitions:

Freud

Sigmund Freud was the founder of psychoanalysis, a method for treating psychopathology through dialogue between a patient and a psychoanalyst.

Depression

A mental health disorder characterized by persistently depressed mood or loss of interest in activities, causing significant impairment in daily life.

Clinical Interviews

A method used in psychology to gather information about an individual's psychological state, history, and symptoms through a structured conversation.

Behavioral Assessments

Evaluative techniques and tools used to understand and measure individuals' observable and measurable behaviors within a specific context.

Related Questions