Consider a project having the following seven activities:
Optimistic Most likely Pessimistic
Immediate Time (o)Time (m)Time (p)
Activity Predecessors (weeks)(weeks)(weeks)
A none 2 3 4
B A 4 4 8
C A 3 5 7
D B 5 5 5
E B, C 3 6 7
F D 4 5 9
G E, F 3 3 7
(a)What is the expected time for each activity?
(b)What is the expected project completion time?
(c)What is the critical path?
(d)What is the variance for each activity?
(e)What are the expected time and variance of each path?
(f)What is the probability that the project will be completed in less than 24 weeks?


Definitions:

Performance Measures

Metrics and criteria used to evaluate and track the effectiveness, efficiency, or quality of an employee's work output or an organizational process.

Institutional Review Board

A committee that reviews and monitors research involving human participants to ensure ethical standards are met.

American Psychological Association

The leading scientific and professional organization representing psychology in the United States, dedicated to promoting health, education, and human welfare.

National Science Foundation

An independent federal agency in the United States created to promote the progress of science; to advance the national health, prosperity, and welfare; and to secure the national defense.

Related Questions