Consider a project having the following ten activities:
Optimistic Most likely Pessimistic
Immediate Time (o)Time (m)Time (p)
Activity Predecessors (weeks)(weeks)(weeks)
A none 1 5 9
B A 6 6 6
C A 3 5 9
D A 2 4 6
E B, C 4 4 4
F D 4 7 8
G E 2 2 8
H E, F 7 8 9
I F 4 6 9
J G, H, I 3 5 7
(a)What is the expected time for each activity?
(b)What is the expected project completion time?
(c)What is the critical path?
(d)What is the variance for each activity?
(e)What are the expected time and variance of each path?
(f)What is the probability that the project will be completed in less than 30 weeks?
Creative Behaviour
Involves actions aimed at generating new ideas, processes, or solutions within a given context or field.
Identity Shift
A process by which an individual's self-perception and presentation to others change, often due to new experiences or roles.
Open Innovation
A business management model that encourages companies to acquire external ideas and internal inventions to accelerate innovation and market adoption.
In-house R&D
Research and Development activities carried out within an organization, as opposed to outsourcing or external collaborations.
Q7: If there is a common refrigerator for
Q14: When there is insufficient inventory to satisfy
Q33: _ occurs among individuals without regard to
Q58: If you are a member of a
Q71: If your company offers a retirement plan,
Q76: Teams should strive toward creating synergy.
Q79: Unions negotiate on behalf of employees and
Q80: Describe how workload is computed for a
Q82: . What type of aggregate plan sets
Q94: Define Johnson's rule.