Consider a project having the following seven activities:
Normal Normal Crash Crash Maximum
Immediate Time Cost Time Cost Weeks
Activity Predecessors (weeks) ($) (weeks) ($) Reduced
A none 4 3,000 3 5,000 1
B A 9 5,000 7 8,000 2
C A 4 7,000 4 7,000 0
D B, C 6 6,000 4 8,000 2
E C 8 4,000 6 8,000 2
F D 3 4,000 2 9,000 1
G E, F 4 2,000 2 7,000 2
(a)What is the expected project completion time?
(b)What is the critical path?
(c)What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks? By five weeks?


Definitions:

Blog Mining

the process of analyzing blog content to extract insights, trends, and patterns for applications in market research, sentiment analysis, and customer feedback.

Participant Blogs

A research technique that involves recruiting subjects to blog about a specific topic on a regular basis over the course of a relatively short period of time.

High-involvement Products

Products that carry a high price tag or high personal importance and risk to the buyer, often requiring an extensive decision-making process before purchase.

In-store Promotion

Marketing strategies used within a retail environment to attract customers to specific products or offers.

Related Questions