Consider a project having the following ten activities:
Normal Normal Crash Crash Maximum
Immediate Time Cost Time Cost Weeks
Activity Predecessors (weeks) ($) (weeks) ($) Reduced
A none 7 3,000 6 6,000 1
B A 8 5,000 6 9,000 2
C A 2 2,000 1 3,000 1
D A 4 3,000 4 3,000 0
E B, C 9 4,000 7 6,000 2
F C, D 6 4,000 4 9,000 2
G E 2 3,000 2 3,000 0
H E, F 9 4,000 7 7,000 2
I G 1 4,000 1 4,000 0
J H, I 8 2,000 6 7,000 2
(a)What is the expected project completion time?
(b)What is the critical path?
(c)What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks? by five weeks?
Research Hypothesis
A statement predicting the relationship between variables in a study, opposing the null hypothesis.
ANOVA
Short for Analysis of Variance, a statistical method used to compare means of three or more samples.
Second Grouping Factor
A secondary variable used in an analysis to categorize or group data, allowing for comparisons across different levels of this variable.
4 × 3 Factorial Design
A statistical test used in experiments involving two independent variables, one with four levels and the other with three levels, to determine their effect on a dependent variable.
Q2: At work, you have the obligation to
Q5: _ is how the receiver identifies to
Q10: Project managers can evaluate whether the _
Q24: When there is conflict, the first thing
Q25: A successful business presentation begins with:<br>A) A
Q25: Most companies do not use teams to
Q51: An end item has no parents.
Q51: It is acceptable to sell and frequently
Q56: When talking with an executive or senior
Q68: In regard to leadership:<br>A) Not all managers