The Tulsa Company Allocates Overhead Based on a Predetermined Overhead

question 4

Essay

The Tulsa Company allocates overhead based on a predetermined overhead rate of $9.00 per direct labor hour. Job S35 required 8 tons of direct material at a cost of $600.00 per ton and took employees who earn $21.00 per hour a total of 80 hours to complete. What is the total cost of Job S35?