The Standard Factory Overhead Rate Is $7

question 9

Multiple Choice

The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead) based on 100% capacity of 80,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows: The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead)  based on 100% capacity of 80,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows:   What is the amount of the factory overhead volume variance? A)  $12,000 unfavorable B)  $12,000 favorable C)  $14,000 unfavorable D)  $26,000 unfavorable What is the amount of the factory overhead volume variance?


Definitions:

Economies of Scope

Cost advantages that enterprises obtain through the variety of products rather than through a high volume of a single product.

Cost Function

A mathematical relationship describing how production costs change with changes in the quantity of output produced.

Economies of Scope

Economies of scope occur when it is more cost-effective for a company to produce two or more products together rather than separately.

Cost of Producing

The total expenditure incurred in manufacturing a product or providing a service, including materials, labor, and overheads.