Given the following data:
The end product J is made from components K and L. Component K is made from M and N. The authorized MPS calls for 10 J to be completed in week 2, 30 J to be completed in week 3, 40 J to be completed in week 5, and 50 J to be completed in week 6. There is a scheduled receipt of 120 L in week 2.
(a) What are the gross requirements for K, L, M and N?
(b) What are the planned orders for K, L, M and N?