Examlex
Direct Direct Direct Materials Labour Cost Labour Hours
Job 400 $200 $800 40
Job 401 250 200 10
Job 402 500 600 32
Sparkle Company uses job costing and applies overhead using an actual costing system using direct labour hours as the allocation base. This period's estimated overhead cost is $400,000, estimated direct labour cost is $500,000 and estimated direct labour hours are 25,000. This period's actual overhead cost was $420,000, actual direct labour cost was $390,000, and actual direct labour hours were 20,000.
What is the total manufacturing cost of Job 402?
Forrester Research
An American market research company that provides advice on existing and potential impact of technology.
Q49: Heesacker Co. sells a product with a
Q51: Beginning WIP units were 8,000, and 40,000
Q67: Standard cost equivalent units are calculated the
Q83: Following are production data for a process
Q83: The Harris Co. sells three products in
Q92: Which of the following do managers use
Q100: What should determine the choice of cost
Q115: Macey Company uses a weighted-average process costing
Q121: Le Château Joyal is an historic hotel
Q139: Which is an advantage of an ABC