Robin Construction Company began a long-term contract in 2018. The contract price was $800,000. The estimated cost of the contract at the time it was begun was $500,000. The actual cost incurred in 2018 was $350,000. The contract was completed in 2019 and the cost incurred that year was $125,000. Under the percentage of completion method: