Examlex

Solved

The Total Completion Time Is 25 Days

question 47

Multiple Choice

The total completion time is 25 days.Task A is planned to take seven days.Task B is planned to take five days.Task C is planned to take eight days.The tasks have a serial relationship.Task A takes nine days to be completed instead of seven days.How much slack does the project have now that Task A is finished?


Definitions:

Automatic Thinking

Quick, reflexive thoughts that occur without conscious effort, often based on schemas or past experiences.

Deliberate Thinking

The process of consciously and intentionally focusing on specific thoughts or problems, often associated with careful decision-making and problem-solving.

Efficiency

The ability to accomplish a task or produce a desired outcome with the least amount of waste, expense, or unnecessary effort.

Information

Data processed or stored by a system, person, or organization that is useful for making decisions or solving problems.

Related Questions