PERT Times
Estimated durations for activities involved in a project, used in the Program Evaluation and Review Technique for planning and scheduling.
Optimistic Time
The “best” activity completion time that could be obtained in a PERT network.
Probable Time
An estimate of the amount of time that might reasonably be expected to be needed to complete a specific task or project.
Expected Activity Time
In project management, it's the best estimate of the time required to complete a task, considering various factors like resources and complications.
Q1: According to Sartre,we are "condemned to be
Q5: Girard accepts a job with Deep Vault
Q17: For nonrival goods like pay-per-view television programmes,the
Q25: Quint rents a riding mower from Rent-All,Inc.Quint
Q28: Kade and Lila each press certain quantities
Q28: An insurance application is part of the
Q35: (Figure: Seasonally Adjusted Unemployment Rate)Use Figure: Seasonally
Q52: According to economic models of trade,when Canada
Q53: Using marginal analysis to decide whether to
Q65: Whenever a species is threatened with extinction,it