If the Appropriate Scheduling Equation for Task a of a Project

question 42

Multiple Choice

If the appropriate scheduling equation for task A of a project were W = D * U,and it was initialized so that W = 40d,D = 10d,and U = 4 resources,and task A is an effort-driven activity,correctly balance this equation if the value for U is changed from 4 to 5.To balance the equation,the altered variable and its new value are __________.


Definitions:

Human Efficiency

The effectiveness with which humans perform tasks, often evaluated in terms of speed, accuracy, and energy expenditure.

Dynamometer

A device for measuring force, torque, or power. For example, in a clinical setting, it can measure the strength of different muscle groups.

Distraction-Conflict Theory

A theory suggesting that the presence of others can increase arousal and facilitate performance on familiar tasks but may hinder performance on complex tasks due to attentional conflict.

Evaluation Apprehension Model

A theory suggesting that anxiety about being evaluated by others can lead to increased or decreased performance depending on the individual and the context.

Related Questions