The Arrangement of All Activities (And,in Some Cases,events)in a Project

question 32

Multiple Choice

The arrangement of all activities (and,in some cases,events) in a project arrayed in their logical sequence and represented by arcs and nodes is called a __________.


Definitions:

Time-Driven Activity-Based Costing

An accounting method that allocates costs based on actual activities performed and the time it takes to complete those activities.

Tech Support Department

A functional division within a company that provides technical assistance and support services to its customers or users.

Customer Cost Analysis

An evaluation technique to determine the total cost incurred by a business to produce, sell, and distribute a product to a specific customer.

Total Cost Assigned

The aggregate cost allocated to a specific product, job, or project, including direct and indirect costs.