Task H Has Duration of 5 Days,an Early Start of 25

question 56

Multiple Choice

Task H has duration of 5 days,an early start of 25 days,an early finish of 30 days,a late start of 25 days,and a late finish of 30 days.There are __________ days of slack for task H.