With practice, we can markedly increase the duration information can be held in sensory storage.


Definitions:

Critical Path

The longest sequence of activities in a project plan, which determines the shortest possible duration for completing the project.

Probability

A measure of the likelihood that an event will occur, expressed as a number between 0 (impossible) and 1 (certain).

Variance

A statistical measure that represents the degree of spread or dispersion of a set of values from their mean.