Sullivan Inc

question 100

Multiple Choice

Sullivan Inc.reports the following information about resources.At the beginning of the year,Sullivan estimated it would spend $180,000 for materials,$42,000 for purchasing,$35,000 for setups,and $36,000 for repairs. Sullivan Inc.reports the following information about resources.At the beginning of the year,Sullivan estimated it would spend $180,000 for materials,$42,000 for purchasing,$35,000 for setups,and $36,000 for repairs.   Compute unused resource capacity for repairs for Sullivan. A) $4,800. B) $10,800. C) $6,000. D) $3,600. Compute unused resource capacity for repairs for Sullivan.


Definitions:

Special Order

A one-time order that is not considered part of the company’s normal ongoing business.

Opportunity Costs

The benefits a person or business foregoes by choosing one alternative over another.

Idle Capacity

Unused production capability within a manufacturing plant or business operation, often due to lack of demand or inefficiency.

Drop a Product

The decision by a company to cease the production and sale of a particular product.