Lo-crete produces quick setting concrete mix.Production of 200,000 tons was started in April,190,000 tons were completed.Material costs were $3,152,000 for the month while conversion costs were $591,000.There was no beginning work-in-process;the ending work-in-process was 70% complete.What is the cost of the product that was completed and transferred to finished goods?